Yankee Gas expansion update for Oct. 6-10

Crews will continue construction operations on the 3.5-mile natural gas pipeline this week, Oct. 6-10.

A crew from GPL Construction will begin to install gas facilities to Wilton Meadows and The Greens at Cannondale.

A crew from Henkels and McCoy will continue with the installation of pipe on Wolfpit Road, focusing on the Metro-North Railway bridge crossing.

The project, originally expected to be completed in November, is ahead of schedule and could be completed by the middle of this month.

Information: (860) 665-4644, wiltonexpansion.com, gas.expansion@nu.com.