Gas line construction activities this week (Sept. 15-19)

For the week of Sept. 15-19, crews will continue working on the 3.5-mile natural gas pipeline.

One crew from GPL Construction will begin installing pipe along Route 7 adjacent to Wilton High School. The crew will be working from Catalpa Road working north.

A second crew from GPL Construction will continue to install pipe on Horseshoe Road working south toward Wolfpit Road.

A crew from Henkels and McCoy will continue with the installation of pipe on Wolfpit Road, focusing on the Norwalk River bridge crossing.

Information: wiltonexpansion.com, gas.expansion@nu.com, 860-665-4644.